Facts
- York (principal/developer) engaged Tomkins (builder) to construct two residential apartment projects.
- A payment dispute arose under the Building Industry Fairness (Security of Payment) Act 2017 (Qld) (BIF Act), proceeding to adjudication.
- The dispute centred on façade works, including issues of:
- extent of completion, and
- alleged defects / non-compliant work.
- Tomkins’ payment claim:
- Valued façade works at approximately 46% complete;
- Applied a deduction of ~$4.76 million for “defective work”, said to reflect the estimated cost of rectification.
- York’s position:
- The façade works were only about 29% complete;
- The claimed deduction was not properly characterised as “defective work”, but rather an attempt to value incomplete works;
- The builder had not established actual defects or a proper basis for rectification costs.
- The adjudicator:
- Rejected that the works were proven to be defective in the strict sense;
- Accepted that the builder had raised legitimate concerns about compliance (including absence of a Form 15 certification);
- Found York had not adequately responded to those concerns;
- Allowed a deduction equal to the estimated rectification cost (~$4.76m) as a proxy for valuing work not in accordance with contract under s 72(1)(b)(iv).
- At first instance, the primary judge found aspects of the adjudicator’s reasoning to be problematic but ultimately upheld the decision, finding no jurisdictional error.
Decision (Court of Appeal)
- The Court of Appeal dismissed York’s appeal with costs.
- Key findings:
- The central statutory task for the adjudicator is to decide the amount of the progress payment under s 88 of the BIF Act.
- While parts of the adjudicator’s reasoning were described as “illogical” or internally inconsistent, that alone does not establish jurisdictional error.
- The adjudicator:
- Considered the contract, submissions, and payment materials;
- Grappled with the façade issue (completion vs defects);
- Ultimately valued the work by reference to rectification cost, which is expressly permitted under s 72 where work is not in accordance with the contract.
- Even if the adjudicator:
- conflated defect and valuation concepts, or
- failed to make a clear finding of “defect”,
this did not mean he failed to perform the statutory task.
- The Court emphasised that judicial review is limited—errors in reasoning will only invalidate a decision if they demonstrate a failure to exercise jurisdiction (not merely a flawed exercise of it).
Key Takeaways for Industry
1. Very limited scope to challenge adjudication decisions
- This decision reinforces that Security of Payment adjudications are highly resistant to judicial review.
- Even:
- logical inconsistencies, or
- imperfect reasoning
will not suffice unless they show the adjudicator did not actually perform the statutory task.
2. “Illogical” reasoning ≠ jurisdictional error
- The Court accepted the adjudicator’s reasoning was, in parts, difficult to reconcile.
- However, provided the adjudicator:
- addresses the dispute, and
- reaches a conclusion on valuation,
the courts will not intervene.
Practical implication:
Parties should not expect to “fix” an unfavourable adjudication outcome via judicial review.
3. Rectification cost remains a powerful valuation tool
- The case confirms that adjudicators can:
- value work by reference to the cost of rectification,
even where: - defect findings are not clearly made, or
- the issue overlaps with incomplete work.
- value work by reference to the cost of rectification,
- This reflects the flexibility under s 72(1)(b)(iv) of the BIF Act.
Practical implication:
Respondents can deploy rectification cost arguments strategically, even where defect evidence is contested or incomplete.
4. Failure to respond to defect allegations is risky
- York’s failure to:
- engage substantively with defect concerns, and
- provide contractual certification (Form 15),
was influential in the adjudicator’s reasoning.
Practical implication:
Claimants must:
- directly address alleged defects in payment schedules and adjudication responses;
- ensure contractual certification requirements are strictly complied with.
5. Distinction between “defects” and “valuation” may blur
- The case shows that, in practice:
- arguments about defective work,
- non-compliant work, and
- extent of completion
may be treated interchangeably in adjudication.
Practical implication:
Submissions should be framed holistically, addressing:
- completion percentages,
- compliance with contract, and
- rectification cost—rather than treating them as siloed issues.
6. “Quick and dirty” regime reaffirmed
- The Court reaffirmed that the BIF Act operates as a rapid, interim payment regime, not a forum for perfect reasoning.
Bottom line:
Adjudication outcomes will stand unless there is a clear failure to exercise jurisdiction—not merely a flawed decision.